This is Phase 1 of a three stage programme of road and cycle improvements to the A180 and its link roads. This phase will deliver essential maintenance to two key industrial roads directly linked to A180: Moody Lane and Woad Lane, and increase sustainable travel options for cyclists and pedestrians, within key employment zones.

Both roads (Moody Lane and Woad Lane) lead to important employment sites in Grimsby, access to the Port of Grimsby and both link to the junction of the planned new industrial link road – the Humber Link Road. This road will connect key EZ sites and other industrial areas with the Ports and the new shared use cycle/footway will complete the off-road routes for cyclists travelling through to the Immingham industrial area.

Project Dates

March 1, 2019 - July 31, 2020

Project Sponsor

North East Lincolnshire Council

Location

Moody Lane and Woad Lane, Grimsby

Funding

TOTAL PROJECT EXPENDITURE £2,622,110.00
Profiled Achieved overall up to end of Q4 20/21
LGF Spend £2,094,688.00 £2,094,688.00
Private Spend £        3,000.00 £        4,500.00
Public Spend £    524,422.00 £    432,781.00

Outputs

  Profiled Achieved overall up to end of Q4 20/21
Construction jobs 36 63
Resurfaced roads (Km) 2.81 3.123
New cycleways completed & open for public use (Km) 1.25 3.884
Resurfaced footway (Km) 3.23 0.545
Resurfaced shared use cycle/footway (Km) 0.95 0.951

Approval Status

Business case approved

Delivery Status

Completed

Last updated: April 4, 2022