This project will deliver a newly constructed low carbon 15,000ft² (1,394m²) factory unit. This would be the first building to be constructed on this site, and help to establish the site as a potential base for advanced engineering and manufacturing companies.

 

The project will deliver a 15,000ft² (1,394m²) light industrial unit, designed for an advanced engineering manufacturing business.  The unit will be a mix of office, research and development, manufacturing and distribution space and be suitable for a range of business uses in the long term.

 

Project Dates

January 2, 2019 - March 9, 2021

Project Sponsor

North East Lincolnshire Council

Location

The project activities will be carried out at the Stallingborough Enterprise Zone site, the largest of the Enterprise zones located in North East Lincolnshire and part of the South Humber Industrial Investment Programme (SHIIP). The site is close to Immingham Docks and has direct access to the A180, and the Council have invested £23m into the project to bring the scheme forward through land acquisitions, mitigation sites and infrastructure to give access to the land which will commence early 2019.

Funding

TOTAL PROJECT EXPENDITURE £ 2,716,880.00
Profiled Achieved overall – up to end of  Q4 20/21
LGF Spend £   950,000.00 £   950,000.44
Public Spend £1,766,880.00 £1,460,933.00

Outputs

  Profiled Achieved overall – up to end of Q4 20/21
New jobs 80 0
Safeguarded jobs 21 0
Construction jobs 29 116
Area of land reclaimed/redeveloped or assembled (ha) 0.607 0.809
Commercial floor space created (m2) 1,394 1,460
Commercial floor space occupied (m2) 1,394 0
Number of commercial premises that now have access to improved broadband 1 1
Number of enterprises receiving non-financial support 1 1

Approval Status

Business case approved

Delivery Status

Started

Last updated: September 10, 2021