Programme of cycle infrastructure upgrade and provision of new cycle facilities where there are gaps in the network across the City of Hull and adjoining urban areas of East Riding of Yorkshire. The investment will support safe and sustainable travel to work, reducing congestion and improving air quality and well-being.
The following priority routes have been identified:
- Cottingham to Hull City Centre
- Beverley Road (A1079)
- Former Hornsea rail line
- A number of ‘quick win’ routes throughout the city of Hull
Project Dates
September 1, 2020 - June 30, 2023
Project Sponsor
Hull City Council
Location
Cycle trails and routes around the Hull and immediately adjoining East Riding of Yorkshire.
Funding
TOTAL PROJECT EXPENDITURE | £3,806,000.00 | |
Profiled | Achieved up to end of Q4 22/23 | |
GBF Spend | £2,700,000.00 | £2,700,000.00 |
Public Spend | £1,106,000.00 | £ 830,603.00 |
Outputs
Profiled | Achieved up to end of Q4 22/23 | |
Number of new apprenticeships | 1 | 1 |
Construction jobs | 19 | 19 |
Roads/cycle lanes/walkways maintained/built (Km) | 12.65 | 12.1 |
Approval Status
Business case approved
Delivery Status
Started