This project represents the second phase of a programme that was previously funded through the York, North Yorkshire & East Riding LEP Growth Deal as a DfT retained scheme.
There are two components:
In the East Riding, of a package of improvements will be undertaken on the A614 from south of Boothferry Bridge to Holme Road (Caville bends), Eastrington.
In Hull, inlay/overlay treatment to the A165 Holderness Road to Ganstead, which can be delivered in full in 2020/21.
Both schemes will effect important improvements to journey to work routes that will make it easier for travel to key employment sites and other services.
Project Dates
August 31, 2020 - November 1, 2021
Project Sponsor
East Riding of Yorkshire Council
Location
HU11 4BE (East Riding of Yorkshire Council area)
Funding
TOTAL PROJECT EXPENDITURE | £3,080,000.00 | |
Profiled | Achieved overall – up to end of project | |
GBF Spend | £2,000,000.00 | £2,000,000.00 |
Public Spend | £1,080,000.00 | £1,080,000.00 |
Outputs
Profiled | Achieved overall – up to end of project | |
Safeguarded jobs | 20 | 20 |
New apprenticeships | 2 | 2 |
Roads/cycle lanes/walkways unlocked (Km) | 6.85 | 6.85 |
Approval Status
Business case approved
Delivery Status
Completed