Highways England’s A160/A180 Port of Immingham Improvement Scheme was completed in 2017, improving the strategic road connection to the Port of Immingham. This project will undertake essential maintenance on the local roads to complement the A160 scheme.
This project will seek to improve the condition and quality of the highway asset and ensure they are of a suitable standard to accommodate existing traffic flows and are also capable of handling additional traffic, from the growth of existing industries or new developments within the area. Furthermore to help improve sustainable travel linkages from North and South Killingholme to the area, it is proposed that the existing cycleway on Staple Road should be upgraded and a new facility provided along Church Lane.
Project Dates
February 19, 2019 - March 31, 2022
Project Sponsor
North Lincolnshire Council
Location
South Humber Gateway (Rosper Road, Eastfield Road, Chasehill Road, Haven Road, Humber Road)
Funding
TOTAL PROJECT EXPENDITURE | £3,408,342.00 | |
Profiled | Achieved overall up to end of Q4 20/21 | |
LGF Spend | £2,497,280.00 | £2,497,280.13 |
Public Spend | £ 911,062.00 | £ 796,062.00 |
Outputs
Profiled | Achieved overall up to end of Q4 20/21 | |
New jobs | 9 | 9 |
Safeguarded jobs | 11 | 1 |
Construction jobs | 40 | 40 |
Resurfaced roads (Km) | 9.2 | 9.52 |
New cycleways completed & open for public use (Km) | 0.52 | 0.24 |
Approval Status
Business case approved
Delivery Status
Started
View project homepageAll locations are approximate.