Please note this project is now being monitored by the Greater Lincolnshire Local Enterprise Partnership.

Stallingborough Phase 1B LGF funding will contribute to an extended estate road, and provide associated utilities and drainage enabling phase 1b (15hectares of development). In a prominent location on the A180 and in close proximity to the Ports of Immingham and Grimsby, the Enterprise Zone site will be very attractive to ports, logistics and manufacturing users.  The project will accelerate development for the private sector and underpin NELCs South Humber Industrial Investment Programme.

The project builds on the progress made through an earlier Growth Deal project, Stallingborough Interchange, to enable the development of the Enterprise Zone site.

Project Dates

July 31, 2018 - May 30, 2021

Project Sponsor

North East Lincolnshire Council

Location

Near Stallingborough, North East Lincolnshire

Funding

 

TOTAL PROJECT EXPENDITURE £2,976,580.00
Profiled Achieved overall – up to end of Q4 20/21
LGF Spend £1,600,000.00 £1,600,000.00
Public Spend £1,376,580.00 £1,389,519.00

 

Outputs

 

  Profiled Achieved overall – up to end of Q4 20/21
Construction jobs 21 21
Area of land reclaimed/redeveloped/assembled (ha) 15 0
Commercial floor space created (m2) 10,775 0

Approval Status

Business case approved

Delivery Status

Started

Last updated: April 4, 2022