This scheme is part of a package of new and improved managed workspace offers to meet demand and stimulate economic recovery in Hull and East Riding.

 

BeSpoke resource Centre, Bransholme

An existing multi-purpose building will be converted into a dedicated managed workspace centre with 13-24 units for let, serviced by an on-site management and business advice resource. The conversion works will also improve the energy efficiency and security of the property.

Boulevard, Phase 4

A semi-derelict building will be demolished and a terrace of 7 small business units constructed on the site aimed at small businesses engaged in a variety of B1 uses. The facility will complement the adjacent Boulevard unit factory estate and Louis Pearlman Centre managed workspace.

 

 

Project Dates

October 1, 2020 - July 18, 2022

Project Sponsor

Hull City Council

Location

Zeals Garth, Bransholme, Hull, HU7 4WD

Goulton Street, Hull, HU3 4DL

Funding

TOTAL PROJECT EXPENDITURE £1,446,000.00
Profiled Achieved up to end of Q4 21/22
GBF Spend £500,000.00 £500,000.00
Public Spend £946,000.00 £920,846.00

Outputs

  Profiled Achieved up to end of Q4 21/22
New jobs      46        0
Construction jobs      13        8
Commercial floor space unlocked (m2) 2,149 1,279

Approval Status

Business case approved

Delivery Status

Started

Last updated: February 1, 2023