The project supports Hull City Centre’s transition to new leisure and residential uses. This will be achieved through delivering key development sites and supporting the conversion of empty properties where their traditional use is no longer viable. The project addresses viability issues caused by land conditions, archaeology, contamination, access infrastructure and flood risk.
Project Dates
April 1, 2017 - December 23, 2021
Project Sponsor
Hull City Council
Location
Hull city centre
Funding
TOTAL PROJECT EXPENDITURE | £10,613,374.00 | |
Profiled | Achieved overall – up to end of Q4 20/21 | |
LGF Spend | £2,500,000.00 | £2,500,000.00 |
Public Spend | £8,113,374.00 | £6,467,095.00 |
Outputs
Profiled | Achieved overall – up to end of Q4 20/21 | |
Area of land reclaimed/redeveloped or assembled (ha) | 0.89 | 0.89 |
Buildings demolished | 2 | 1 |
Buildings cleared of asbestos | 2 | 1 |
Approval Status
Business case approved
Delivery Status
Started
View project homepageAll locations are approximate.