The scheme is to provide a large Flood Alleviation Scheme that reduces the flood risk in an economically achievable standard with ranges established by sensitivity testing.
The Target standard will be 1% Annual Exceedance Probability with a 30% allowance for climate change (1:100 year + 30% CC Standard of Protection). This will be refined with sensitivity testing that shall take into account climatic antecedents and other factors
Subject to detailed options appraisal in line with the Detra approved national standards using the ‘Flood Hazard Research Centre- Flood and Coastal Erosion Risk Management- A Manual for Economic Appraisal of Flood Risk.’ The preferred option will include one or all of the following components:
- Construction of a series of large flood storage areas, approximately 300,000 m³
- Construction of new ancillary engineering works
- Construction of real time flow control apparatus
The intervention area centres on the rainfall run-off from the geographical features known as the Westella Valley and Tranby Hill. This is an area of approx 1200 Ha that presents peak flood flows to Analby and the City in excess of 5,000 l/s as was seen in 2007. Because the urban drainage system in the city has a finite drainage capacity this becomes quickly overwhelmed causing significant flooding to properties and business. This scheme will take approximately 4000 properties out of flood risk to the target design standard.
This scheme is complimentary to two other neighbouring flood alleviation schemes, being the Willerby Derringham Flood Alleviation Scheme and the Cottingham and Orchard Park Flood Alleviation Scheme. All three schemes working in unison have a combined beneficial effect on the urban drainage system that has a finite capacity as it relies on pumped operation.
CASE STUDY – Analaby and East Ella PHOTOS – AEEFAS
Project Dates
September 15, 2015 - September 30, 2020
Project Sponsor
East Riding of Yorkshire Council
Location
Villages of Anlaby, Anlaby Common and Anlaby Park and East Ella within the City of Hull, HU10,13,4,5
Funding
TOTAL PROJECT EXPENDITURE | £20,769,000.00 | |
Profiled | Achieved overall – up to end of Q4 20/21 | |
LGF Spend | £ 5,100,000.00 | £ 5,100,000.25 |
Public Spend | £15,669,000.00 | £14,881,913.00 |
Outputs
Profiled | Achieved overall – up to end of Q4 20/21 | |
Safeguarded jobs | 583 | 583 |
Construction jobs | 80 | 162 |
Housing units completed | 0 | 218 |
Area of land reclaimed/redeveloped or reassembled (ha) | 86.78 | 86.78 |
Domestic properties with reduced flood risk | 4,495 | 4,495 |
Commercial floor space with reduced flood risk (m²) | 96,630 | 96,630 |
Approval Status
Business case approved
Delivery Status
Started